Wednesday, 16 November 2011 17:13 |
|
The first of our DRUPS infrastructure has started arriving at
M1!
We have been unpacking the associated electronics such as...
|
|
Read more...
|
|
CitiPower begin work at M1 |
|
Tuesday, 15 November 2011 15:50 |
We thought you might like to see some pictures of Citipower
commencing high voltage feeder work for M1 around Ingles and Turner
street.
|
|
Read more...
|
|
Construction approval for S1! |
|
Tuesday, 15 November 2011 10:02 |
If you haven't already heard, we've just received formal consent
from the City of Ryde to begin construction on our latest next
generation data...
|
|
Read more...
|
|
More Chillers Arrive at B1 |
|
Monday, 14 November 2011 12:48 |
If you happened to be cruising around Brisbane CBD at about 6am
Saturday morning, you would have seen a lot of activity going on at
B1...
|
|
Read more...
|
|
M1 - Data Hall 1 Progress |
|
Friday, 11 November 2011 14:53 |
Data Hall 1 is really starting to take shape at our M1 data
centre!
In the photo above you can see the chilled water pipes
that...
|
|
Read more...
|
|
B1 Special Offer - Limited Time |
|
Thursday, 10 November 2011 16:03 |
Just a reminder that there's only a couple more weeks left for
you to take up our B1 Opening Offer.
If you sign up for space at B1...
|
|
Read more...
|
|
C1 - The Strip Out Continues |
|
Wednesday, 09 November 2011 15:09 |
Upgrading an existing data centre isn't as easy as it sounds. At
our C1 data centre in Canberra which was previously used by
the...
|
|
Read more...
|
|
Tuesday, 08 November 2011 11:30 |
Well, what would you know, after all the excitement yesterday,
the heavy rain and thunderstorms forecasted for Melbourne means
that we have to...
|
|
Read more...
|
|
M1 - Preparing for DRUPS Arrival |
|
Monday, 07 November 2011 15:08 |
Exciting news! We're preparing M1 for the first of our DRUPS
units, which are scheduled to arrive tomorrow. In the photo above
you can see the...
|
|
Read more...
|
|
C1 - The NEXTDC Makeover Begins |
|
Thursday, 03 November 2011 11:25 |
As well as upgrading the data halls and plant equipment at C1 to
bring the facility up to NEXTDC standards, we're also giving
the...
|
|
Read more...
|
|
|
|
|
|
|