M1 - One Week in Data Centre Construction

As we have been showing you this week, there has been plenty going on at M1. We have been installing the chillers, insulating and building the office roof and putting the raised floors in to each of our data halls. We thought that today we would give you a look at the sort of progress we are making in the space of a few days.

You can see how we have been going with the raised floors in the data halls below. This first photo was taken on Tuesday as we were beginning the installation. If you remember our Tuesday blog showed several of our data halls looking like this.

And this picture was taken Thursday morning of the same hall!

Once we got the cooling towers up on to the roof of the building on Wednesday we had to fit out the plinths with the their bases. After they were all on, it seemed like no time at all before we had all the cooling towers up and installed!! Would you believe these next two photos were taken only 2 days apart!

In these two pictures you can see the progress we have made on the roof of the office area. After the insulation arrived two days ago we were held up slightly by the wind in Melbourne but now we just about have a roof!

 

Add comment


Security code
Refresh

  • NEXTDC

  • L4, 88 Creek St
  • Brisbane QLD 4000
  • +61 7 3177 4777
  • info@nextdc.com
  • ABN 35 143 582 521