We are really excited today because fibre for one of our customers has been installed, terminating at M1 as you can see in the photo above. There will be plenty more of this happening over the coming
weeks so watch this space!
There’s also plenty happening at the front of the data centre. As you can see in the photo above, the pre-cast panels at the entrance on the Lorimer Street side are being installed! We can't look away for a second
without its appearance changing so it's going to be awesome to see how it progresses over the next few weeks.
With the progress on the area at the entrance to the data centre, our onsite staff have had to downsize
their portable office so that they aren't in the way! Here you can see their new office arriving on the
back of a truck. They aren't too upset about the small-looking office space because pretty soon they will be in their
brand new offices overlooking the Melbourne sky line!
|