Monday, 30 April 2012 15:48 |
While the construction team at our M1 data centre are busily working on getting the 3 ground floor data halls ready to go live, we have also been making some progress upstairs on Level 1, where we will have 3 more data halls.
These photos show halls 4, 5 and 6. We have painted and sealed all surfaces, and we're starting on construction of the main access corridor for the Level 1 cross connect rooms.
The actual fit out of these Level 1 data halls will form part of the stage 2 project at M1. However, with the number of customers signed up to take space in M1 increasing all the time it won't be long before these three data halls are needed!
|