Friday, 25 May 2012 14:59 |
If you're a regular reader of our blog you might know we have a hall going live this weekend. As you can see here though the other data halls are coming along very nicely down at C1 too. This hall is scheduled to go live in early to mid July as part of phase 1 of the build which will also include data halls 1, 2 and a telco hall.
In these photos you can see some of the underfloor cabling and the first chilled water pipes have been installed. The next step for this hall will be the installation of the captive outlets and more lagging of chilled water pipes so that the floor can go in.
Below You can see a close up of one of the chilled water pipes which sits underneath the raised floors to cool the hall. These are part of the multiple compressor configuration cooling system down at C1.
Next week we will have heaps of info on M1 as it gets closer to completion so make sure you check back!
|